题目描述

An IT company is working on a large project. The project is broken into N modules and distributed to different teams. Each team can work parallelly. The amount of time (in months) required to complete each module is given in an array duration[ ] i.e. time needed to complete i^{th} module is duration[i] months.
You are also given M dependencies such that for each i (1 ≤ i ≤ M) dependencies[i][1]^{th} module can be started after dependencies[i][0]^{th} module is completed.
As the project manager, compute the minimum time required to complete the project.
Note: It is guaranteed that a module is not dependent on itself.
Example 1:
Input:
N = 6, M = 6
duration[] = {1, 2, 3, 1, 3, 2}
dependencies[][]:
[[5, 2]
[5, 0]
[4, 0]
[4, 1]
[2, 3]
[3, 1]]
Output:
8
Explanation:
The Graph of dependency forms this and
the project will be completed when Module
1 is completed which takes 8 months.
Example 2:
Input:
N = 3, M = 3
duration[] = {5, 5, 5}
dependencies[][]:
[[0, 1]
[1, 2]
[2, 0]]
Output:
-1
Explanation:
There is a cycle in the dependency graph
hence the project cannot be completed.
Your Task:
Complete the function minTime() which takes N, M, duration array, and dependencies array as input parameter and return the minimum time required. return -1 if the project can not be completed.
Expected Time Complexity: O(N+M)
Expected Auxiliary Space: O(N)
Constraints:
1 ≤ N ≤ 10^{5}
0 ≤ M ≤ 2*10^{5}
0 ≤ duration[i] ≤ 10^{5}
0 ≤ dependencies[i][j] < N

输入格式

见题面

输出格式

见题面

样例输入
N = 6, M = 6 duration[] = {1, 2, 3, 1, 3, 2} dependencies[][]: [[5, 2] [5, 0] [4, 0] [4, 1] [2, 3] [3, 1]]
样例输出
8